A FULL UPDATE ON THE TOURMALINE & CLUBHOUSE DEVELOPMENT
|
|
|
|
2025 Lauchernalp Swiss Resort, Investor Report & Building Summary
|
|
|
Dear Investors and Partners,
As we close the year, we are pleased to share an update on the progress of the Lauchernalp Swiss Resort development. The past months have brought both tremendous challenges and remarkable achievements, and we are proud to report that the vision for Lauchernalp remainsfirmly on track.
|
|
|
|
|
|
Project Progress Overview &
Building Summary
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Unprecedented Event, 28 May 2025
|
|
|
After the winter season and once the snow had cleared, we officially began construction on 16 May 2025. Our teams mobilized quickly, ready to move forward at full speed.
|
|
|
Only days after opening the site, the Lötschental Valley experienced an event unlike anything seen before.
|
|
|
Only days after opening the site, the Lötschental Valley experienced an event unlike anything seen before. On 28 May, approximately 9 million cubic meters of mountain collapsed onto Blatten village, displacing 300 residents and dramatically impacting the valley’s landscape. This required a careful reassessment of the region and project strategy.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Our Commitment
to the Vision
|
|
|
The Lauchernalp team reaffirmed its commitment to supporting job sustainability, maintaining momentum for tourism essential to the valley’s survival, and providing a positive focus for the community. Instead of pausing for another year, we made the strategic decision to accelerate construction and uphold our target opening of December 2026.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
EXCEPTIONAL RESULTS IN 2025
|
|
|
|
Construction Achievements
|
|
|
|
|
|
|
Moving 5,000 m³ tons of earth.
|
|
|
|
|
|
|
|
Installing all wall anchors for the Tourmaline building and the Clubhouse
|
|
|
|
|
|
|
|
Completing all services installation
|
|
|
|
|
|
|
|
Casting and securing
the concrete and
steel slab
|
|
|
|
|
|
|
|
|
|
|
|
|
Despite losing nearly three months of construction time due to the natural disaster, our teams delivered extraordinary results. As of the 21 November 2025 site closure, due to snow and the arrival of winter, we are still on schedule for a December 2026 opening.
|
|
|
We extend special thanks to SBP Engineering, Zengaffinen Concrete Construction, Construction Director Hans Jacob, and all site and surveying teams for their dedication.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Top Structure &
Interior Design
|
|
|
Rubner will continue building the top structure through the winter months so that when spring arrives, final preparation and installation can begin immediately. All interior design selections and furniture procurement with Baur have been completed.
|
|
|
|
|
|
|
|
|
|
|
|
Exceptional Sales Momentum and Rising Property Values
|
|
|
Sales performance has remained exceptionally strong. Only one sale was lost due to the landslide. Tourmaline has only 2 units remaining out of the 21 units. Chalets are fully sold out for 2025 and 2026, with a waiting list for 2027. Phase 2 – Lazulite will launch in early January 2026.
|
|
|
|
In addition, the average selling price in the resort has increased from CHF 12,000/m² to CHF14,000/m². Our new phases will start at CHF 15,000/m², meaning our clients can already be confident that their properties have gained value.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
We extend our heartfelt thanks to our full development team for their belief and resilience throughout this year. To our clients, investors, and the local community, your ongoing support has been crucial to our progress.
We look forward to sharing our next update in the spring. For now, we wish you a reflective and peaceful festive season.
Warm regards,
The Lauchernalp Swiss Resort Development Team
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Toni Enderli
+ 41 796 76 31 55
toni@roeswiss.ch |
|
|
|
|
|
|
|
Dean Harley
+41 79 697 74 85 dean@legacyinvestments.ch
|
|
|
|
|
|
Jannis Fragakis
+41 76 518 69 89
jannis@roeswiss.ch
|
|
|
|
|
|
|
Jaka Jakopic +41 79 835 21 86
jaka@roeswiss.ch |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sarah Wolfisberg
+41 79 470 16 19
sarah@roeswiss.ch |
|
|
|
|
|
|
|
|
Cai Weston
+41 79 459 41 73
cai@roeswiss.ch |
|
|
|
|
|
|
|
|
Wayne Lawson
+27 76 809 15 97
wayne@realgroup.co.za |
|
|
|
|
|
|
|
|
Lesley van Zyl
+27 72 018 87 51
lesley@realgroup.co.za |
|
|
|
|
|
|
|
|
|
|
|
|
|
|